PROJECT HIGHLIGHTS:

Technology: Combined Cycle Gas Turbine

Major Equipment:

  • Mitsubishi M501GAC Combustion Turbine

  • Vogt Power Heat Recovery Steam Generator

  • Toshiba Americas Steam Turbine

Fuel: Natural Gas

Net Output:  475 MW (nominal)

Location: Kings Mountain, Cleveland County, North Carolina

Investment: $440 Million

Jobs Created: 300 During Construction | 20 Full-Time During Operation

Start Construction: 3Q 2015

Commercial Operation Date:  August 9, 2018

 August 2018 - Completion

August 2018 - Completion

 Representatives from Cleveland County toured the plant. During their visit, they discussed NTE’s significant positive impact on the local economy. Pictured here are Shane Fox, CFO of the County, Kerrie Melton, Assistant County Manager, and Doug Bridges, a County Commissioner.

Representatives from Cleveland County toured the plant. During their visit, they discussed NTE’s significant positive impact on the local economy. Pictured here are Shane Fox, CFO of the County, Kerrie Melton, Assistant County Manager, and Doug Bridges, a County Commissioner.

 February 2018

February 2018

 December 2017

December 2017

 October 2017

October 2017

September 2017

July 2017

May 2017

March 2017

January 2017

November 2016

September 2016

July 2016

August 2017

June 2017

April 2017

February 2017

December 2016

October 2016

August 2016

July 2016

July 2016

May 2016

March 2016

March 2016

February 2016

November 2015